> [!IMPORTANT]
>
> 25.12 FREEZE October 27th: Non-bugfix PRs not ready by this date will wait for 26.03.
> 26.04 FREEZE March 11th: Non-bugfix PRs not ready by this date will wait for 26.06.
>
> RC1 is scheduled on _November 10th_
> RC1 is scheduled on _March 23rd_
>
> The final release is scheduled for December 1st.
> The final release is scheduled for April 15th.
## Checklist
@@ -14,3 +14,4 @@ Before submitting the PR, ensure the following tasks are completed. If an item i
- [ ] Tests have been added or modified to reflect the changes.
- [ ] Documentation has been reviewed and updated as needed.
- [ ] Related issues have been listed and linked, including any that this PR closes.
- [ ] *Important* All PRs must consider how to reverse any persistent changes for `tools/lightning-downgrade`